Haimen Phase I 4 * 1000MW domestic critical unit

At 8 o'clock on September 27, 2009, Haimen Phase I 4 * 1000MW domestic critical unit, #2 machine successfully completed 168 hours of full load operation, and successfully put into operation. Haimen Power Plant specially sent a thank-you letter to our company, thanking our company for its excellent service.


Haimen Phase I 4 * 1000MW project is a national key project, and Sugawara Bo Pump provided 4 steam feed pumps and 2 electric feed pumps for the project. After the on-site service of the after-sales service personnel of our company and the good technical support of the technical department, the products are running well, all technical indicators have met the requirements, and successfully completed the full load of 168 hours of operation, marking the company's products in Haimen Power Plant 2 million The generator set has officially entered an important role in commercial operations. At the same time, in view of the good operation of the company's products at work, the four sets of feed pump units in the Haimen Phase I follow-up project are also provided by our company.



Home About us Products Projects News Contact

Address: New&Hi-tech Industrial Development Zone, Zibo, Shandong Province, China. Tel:86-0533-3919586 Email:emz@ebara.cn 

Friendly Links:EBARA CORPORATION EBARA Privacy Policy(Chinese Japanese EnglishEBARA Supply Chain Management

Copyright ? 2018 Ebara Machinery Zibo Co., Ltd. All rights Reserved